Question: 1 / 20

What does LFT represent in Critical Path Analysis?

Latest Failure Time

Latest Finish Time

In Critical Path Analysis, LFT stands for Latest Finish Time. This concept is crucial in project management as it helps determine the latest possible time that a task can be completed without delaying the project as a whole. Understanding the Latest Finish Time is essential for effective scheduling and resource allocation, allowing project managers to identify tasks that are critical to project timelines.

By knowing the Latest Finish Time, project managers can plan for potential delays, ensuring that any adjustments to the schedule will not affect the overall project delivery. It aids in evaluating the flexibility or float of different tasks, allowing for more efficient use of resources and better risk management. Hence, the focus on Latest Finish Time is pivotal in successfully managing project timelines and ensuring that all components of a project align effectively to meet the overarching deadlines.

Latest Follow-up Time

Last Finish Time

Next Question

Report this question

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy